Meeting Date: |
Thursday 15 March 2018 |
Time: |
1.00pm |
Venue |
Council
Chamber |
Present |
John Palairet (In the Chair), Mayor Bill Dalton, Geoff Foster, Councillor Claire Hague, and Councillor Kirsten Wise |
In Attendance |
Chief Executive, Director Corporate Services, Chief Financial Officer [from 1.35pm], Manager Business Excellence and Transformation, Manager People and Capability, Manager Property [to 1.31pm]
Mr Matthew Meacham – Account Manager, JLT Insurance [to 1.31pm] |
Administration |
Governance Team |
Apologies
Nil
Conflicts of interest
Nil
Public forum
Nil
Announcements by the Mayor
Birthday wishes were noted for the Chief Executive
Announcements by the Chairperson
Item 9 on the agenda has been withdrawn; the remaining agenda will proceed as advised.
Announcements by the management
Nil
Confirmation of minutes
That the Minutes of the meeting held on 7 December 2017 were taken as a true and accurate record of the meeting.
|
Notification and justification of matters of extraordinary business
(Strictly for information and/or referral purposes only).
Audit and Risk Committee - 15 March 2018 - Open Minutes
1. Insurance Arrangements
Type of Report: |
Operational |
Legal Reference: |
N/A |
Document ID: |
433370 |
Reporting Officer/s & Unit: |
Caroline Thomson, Chief Financial Officer |
1.1 Purpose of Report
To receive an update from JLT our insurance brokers on the key issues to the Local Government Sector and to consider insurance requirements for Napier City Council for the upcoming financial year 2018/19
Mr Matthew Meacham of JLT insurance provided an overview of the current insurances held by Council; the presentation can be found at Appendix One. The following clarifications were provided in response to questions: · The location of Council’s IT storage is an important part of the business continuity planning underway; should Council elect to transition to the Cloud, it was advised that a particular insurance extension would be required in recognition of the third party supplier. In general the Cloud is considered to have good protections from an insurance perspective. · The last maximum probable loss review was undertaken three years ago and JLT recommend that this be updated. Although there are some costs associated with this process the Committee considered that this would be a valuable investment. It was noted that work is already underway to update the asset information held by Council which will form a good foundation to any review. · The excess in case of natural disaster was discussed briefly, with the implications for earthquake prone buildings. At this point there have not been any specific implications for the lower east coast of the North Island from the Kaikoura quakes, although it lies on the same fault line. It is believed that it would take a major event involving Wellington to impact on insurance capital. · It was noted that central government continues to review the current 60:40 split between central and local government for natural disaster insurances. · Three locations have currently been identified and assessed for suitability for storage of the Hawke’s Bay museum collection ; should other sites be identified, an assessment (i.e. including earthquake prone status, fire safety and so on) would need to be provided to JLT so that an insurance quote could be prepared. · Environmental Impairment insurance recognises that it is generally the owner of a site that is expected to address contamination that may have occurred; this insurance tends to cover gradual contamination issues as an acute event would more likely be covered by public liability or professional indemnity policies. The airport company elected to change the fire retardant foam used on site when it was identified that there may adverse environmental impacts from the previous option; it is not believed that there are other specific risk areas linked to this policy currently. Mr Meacham left the meeting as this item concluded, at 1.31pm. |
a. That the presentation by JLT be received. b. That the Committee make recommendations on changes (if any) regarding the appropriateness of the proposed cover for 2018/19.
|
2. Reappointment of Chair and Independent Member
Type of Report: |
Information |
Legal Reference: |
Enter Legal Reference |
Document ID: |
434449 |
Reporting Officer/s & Unit: |
Adele Henderson, Director Corporate Services |
2.1 Purpose of Report
To advise the reappointment of John Palairet, Chair and Geoff Foster, Independent Member to the Audit and Risk Committee from January 2018 until February 2019.
There was no discussion on this item. |
a. The reappointment of John Palairet, Chair and Geoff Foster, Independent Member to the Audit and Risk Committee be received.
|
3. Draft Long Term Plan 2018-28 Underlying Documents
Type of Report: |
Operational |
Legal Reference: |
Local Government Act 2002 |
Document ID: |
433361 |
Reporting Officer/s & Unit: |
Caroline Thomson, Chief Financial Officer |
3.1 Purpose of Report
That the Committee review and provide feedback to Council on the Long Term Plan 2018-28 underlying documents prior to the final adoption of the reports.
It was noted that while a large amount of reading has been provided to the Committee and to elected members as underlying documentation to the draft Long Term Plan, that this is a good indication of the high level of professionalism of staff, who were commended on the work that has been undertaken to date. Comments were made in discussion on the various supporting documents as follows: Significance and Engagement Policy · An updated policy was adopted by Council in December 2017; it contains a much clearer outline of consultation considerations and processes that will be undertaken in a variety of engagement scenarios.
Significant Planning assumptions · Napier is currently experiencing medium to high level of growth and considering the appropriate levels of infrastructure to service the population has been an important part of the Long Term Planning process. · The document notes the risk that construction costs will be higher than the current forecast inflation adjustment of 2.2%. o The Committee recommended that this risk be made extremely clear, and also be included in the Financial Strategy and the Infrastructure Strategy. o The Committee suggested that it maybe useful to move to using the Construction Index, especially given the size of the Capital Plan (currently the Local Government Cost Index is used), but agreed to hold the current assumption and note the risk. o It was noted that there may be a need to adjust the scope of projects to meet the funding available.
Capital Plan · The Committee noted the size of the Capital Plan and previous challenges that Council has experienced in being able to resource the work. · It was also discussed that there may be some delivery risk with the volume of projects for the region over the next 10 years. · It was noted that a review of internal delivery capacity has been undertaken and approval given to expand resourcing particularly in the areas of project management, design and drafting, and design QA. · It was also noted that for the three major capital projects, external project management and specialist management accounting expertise may be drawn on as required. There may also be existing experience in the construction market in the types of work proposed, which could be leveraged to bring any risk levels down. These projects represent a significant investment in the community and their skilful management is considered of paramount importance. · The Committee commended officers for the thinking captured in the “confidence levels table”; it was noted that Audit NZ are also supportive of the approach. · It was noted that it will be important to manage and maintain the wellbeing and capacity of existing staff throughout the programme, and that any risks or impacts on the cultural shift underway in the organisation from higher numbers of external contractors should be carefully monitored. · The Committee confirmed that they were happy with the risk management actions underway but would continue active monitoring in this space.
Community Outcomes · The process of aligning the outcomes with Sycle (internal system software) is now underway.
Contribution to decision-making processes by Māori · Council’s desire to include and work with Māori in decision making has been clearly outlined.
Council controlled organisations · The Committee supported the decision to ‘shelve’ HB Lass in favour of a more contemporary collaborative model with lower overheads.
Draft Infrastructure Strategy · Work is already underway to build a better understanding of our assets’ condition and performance, and this will continue so that a good foundation of data is held to inform decisions. · The strategy indicates levels of priority for the short, medium and long term to ensure the right things are done at the right times for the right reasons. · Improved modelling is underway for the three waters and roading. · The Committee noted that it should be clearer that the work to be undertaken was necessary to maintain and improve current levels of service; that it was important that the public are aware that the infrastructure spend is required. · The Committee recognised with appreciation the large amount of asset monitoring and planning that has been undertaken by officers across Council.
Draft Financial Strategy · It was noted that while having external debt is a key difference in this Plan to any previous, it is to allow for important investment in infrastructure and the peak forecast debt remains well within levels considered prudent. · It was also noted that the balance sheet offers scope to address natural hazards vulnerability if required. · The Committee were very comfortable that taking on external debt was for good reason and the levels within a prudent range.
Financial documents · Improvements to the financial reporting system now provides for long term integrated reporting. · Rates demonstrate a relatively flat profile over the ten year period. · It is anticipated that external debt will peak in years 3 and 4 of the Plan, and repayment will be completed in year 8.
|
That the Committee a. Receive the Long Term Plan 2018-28 underlying documents · Significance and Engagement Policy · Significant Planning assumptions · Capital Plan · Community Outcomes · Contribution to decision-making processes by Māori · Council controlled organisations · Draft Infrastructure Strategy · Draft Financial Strategy · Statement of Accounting Policies · Prospective Financial Statements · Draft Funding Impact Statement · Financial Prudence benchmarks · Council Funding Policies
b. Document feedback from the review of these documents to be provided to the next available Council meeting.
|
4. Risk Management Report March 2018
Type of Report: |
Information |
Legal Reference: |
N/A |
Document ID: |
433364 |
Reporting Officer/s & Unit: |
Rachael Horton, Manager Business Excellence & Transformation Caroline Thomson, Chief Financial Officer Adele Henderson, Director Corporate Services |
4.1 Purpose of Report
To provide the Audit and Risk Committee (Committee) with an update on progress with risk management work and to report on the highest rated risks.
The Manager Business Excellence and Transformation spoke to the report, noting the following: · An active Risk Committee and network of risk ‘champions’ is now in place. · It is anticipated that a ‘Sycle lead’ role will be recruited in the next few weeks; the role will be responsible for building engagement with an use of the Sycle internal system software over a 24 month contract. · One extreme risk has currently been identified, being Pandora Pond. The pond is now closed (as normally programmed for the year) and treatments are being applied with a view to re-opening as usual for the next season. It was noted that this is a good demonstration of active risk monitoring and management at play. · Following the Committee’s request at its last meeting for a way to track Council’s progress with risk management, a risk maturity roadmap has now been developed, assessing the organisations maturity level (using a four year scale) in seven key areas. Work will be undertaken to review Council’s current status in each area, and what actions would need to be undertaken to the next maturity level. The assessment criteria will be updated regularly to ensure they continue to meet risk management best practice. The Committee were extremely positive about the risk maturity roadmap, noting that it was a ‘very elegant’ piece of work which allows for active monitoring of where Council is at in its risk management journey, and contributes to the continuing formalising and increased visibility of active risk management in the organisation’s culture.
|
That the Committee a. Note the risk management work being undertaken by the NCC Risk Committee b. Receive the reports titled: NCC Risk Maturity Roadmap and Highest rated risks report 2 March 2018.
|
5. Health and Safety Report ending 28 February 2018
Type of Report: |
Information |
Legal Reference: |
N/A |
Document ID: |
441796 |
Reporting Officer/s & Unit: |
Sue Matkin, Manager People & Capability |
5.1 Purpose of Report
To provide the Napier City Council Health & Safety report as at 28 February 2018 for the Committee’s review.
The Committee noted the improvements in Health and Safety reporting and performance over the last year. In response to a question from the Committee it was clarified that many of the near miss reports tend to come from Bayskate, as would be expected from such a physical arena.
|
That the Committee: a. Receive the Napier City Council Health and Safety report as at 28 February 2018.
|
Type of Report: |
Operational |
Legal Reference: |
N/A |
Document ID: |
433362 |
Reporting Officer/s & Unit: |
Caroline Thomson, Chief Financial Officer |
6.1 Purpose of Report
To consider the snapshot report on Napier City Council’s Investment and Debt as at 28 February 2018. See Attachment A
The Chief Financial Officer briefly spoke to the report but there was no discussion on this item.
|
That the Committee a. Receive the snapshot report on Napier City Council’s Investment and Debt as at 28 February 2018
|
7. Sensitive Expenditure - Mayor and Chief Executive
Type of Report: |
Operational and Procedural |
Legal Reference: |
N/A |
Document ID: |
450263 |
Reporting Officer/s & Unit: |
Talia Foster, Corporate Accountant Caroline Thomson, Chief Financial Officer |
7.1 Purpose of Report
To provide the information required for the Committee to review Sensitive Expenditure of the Mayor and Chief Executive for compliance with Council’s Sensitive Expenditure Policy.
The Committee noted that the spend was very modest. The report is intended to be run monthly and will be provided at each meeting of the Committee. There was some discussion about the current report setting, which is in line with the central government practice of individual line item declarations. The Committee indicated it would be comfortable with reporting against categories. It was noted that the Policy is an extremely comprehensive one; along with other policies it is provided to staff via the employee hand book and its associated links. Monthly finance training is also provide to staff on a variety of topics including sensitive expenditure.
|
That the committee a. Receive the report of Sensitive Expenditure for the Mayor and Chief Executive and review for compliance with the Sensitive Expenditure Policy.
|
8. Audit Arrangements for Year Ending June 2018
Type of Report: |
Operational |
Legal Reference: |
Local Government Act 2002 |
Document ID: |
433369 |
Reporting Officer/s & Unit: |
Caroline Thomson, Chief Financial Officer |
8.1 Purpose of Report
To outline the audit arrangements for the audit of the Napier City Council for the year ending 30 June 2018.
The Audit Plan received from Audit New Zealand late on 14 March 2018, was tabled. It was advised that auditors will be on site during April, May and August to undertake reviews. It was a significant advantage that they were now able to be in the same building, as it been difficult while their organisational policy prohibited entry into the designated earthquake-prone Civic Building. It was agreed that a review of Council’s audit provision would be initiated through the Office of the Auditor-General who oversees this process. A short discussion took place on fraud identification and management; policies, processes and data analytics are all in place to ensure the quick identification of any fraud would take place and any issues would be communicated to councillors as soon as reasonably practicable.
|
That the Committee a. Receive the audit arrangements for the year ending 30 June 2018 as set out in the audit arrangement letter from Audit New Zealand.
|
Audit and Risk Committee - 15 March 2018 - Open Minutes
PUBLIC EXCLUDED ITEMS
That the public be excluded from the following parts of the proceedings of this meeting, namely: 1. Internal Audit Data Analytics - Management Actions
|
The general subject of each matter to be considered while the public was excluded, the reasons for passing this resolution in relation to each matter, and the specific grounds under Section 48(1) of the Local Government Official Information and Meetings Act 1987 for the passing of this resolution were as follows:
General subject of each matter to be considered. |
Reason for passing this resolution in relation to each matter. |
Ground(s) under section 48(1) to the passing of this resolution. |
1. Internal Audit Data Analytics - Management Actions |
7(2)(a) Protect the privacy of natural persons, including that of a deceased person |
48(1)A That the public conduct
of the whole or the relevant part of the proceedings of the meeting would be
likely to result in the disclosure of information for which good reason for
withholding would exist: |
The meeting moved into Committee at 2.49pm
Approved and adopted as a true and accurate record of the meeting.
Chairperson .............................................................................................................................
Date of approval ...................................................................................................................... |
Appendix One – JLT Insurance Presentation